How to build a run of show, step by step
A run of show is easy to start and hard to finish. These are the steps, in the order that saves the most rework, with a short worked example for an evening gala.
The short answer
Write down the times you cannot move. List every item in order. Give each one a length and let the start times follow. Add the back-of-house rows, an owner for each row and a few buffers. Check it against the venue's times, walk it with the people who will run it, then send one dated version to everyone.
1. Start from the fixed points
Some times are not yours to choose. Find them first, because everything else has to fit between them.
- Doors, as promised to guests on the invitation or agenda.
- The venue's hard out, and when you can get in.
- Meal service times the kitchen is working to.
- Contracted set lengths for a band, speaker or performer.
- Anything tied to the outside world: a live stream, a curfew, a coach departure.
2. List every item in order
Start with what guests experience: doors, welcome, dinner, keynote, awards, band, goodnight. One row per item. Do not worry about times yet. If two things happen in different rooms at once, they belong on separate lists, one per room.
3. Give each item a length, not a start time
This is the step that saves the most work later. Type in how long each item runs and let each start time be the previous start plus the previous length. Only the fixed points from step 1 get a typed-in time. When the keynote grows by ten minutes, you change one number and the rest of the night moves on its own.
The run of show template has the spreadsheet formulas for this.
4. Add the back-of-house rows
Now add what guests never see but the show depends on: line check, speaker to the green room, microphones fitted, catering clearing plates, the band's changeover. Most of these belong to an item on the main list. Write them that way: "15 minutes before the keynote", not "7:00 PM". If the keynote moves, they should move with it.
5. Put a name on every row
Each row needs one owner, a person and not a department. "AV" does not walk a speaker to the stage. "Ben, stage manager" does. Add the notes that person needs: which microphone, which door, which slide.
6. Add buffers and mark what can be cut
Put a few spare minutes where they cost least: after a meal, before the main speaker, during a changeover. Then decide in advance what you would shorten or drop if the night runs long, and write it on the row. That decision is easy the week before and hard at 8:40 PM.
7. Check it against everyone else's document
- The agenda the client sent to guests. The times must agree.
- The venue's banquet event order. Its service times must match yours. See BEO vs run of show.
- Venue access, dock bookings and the hard out.
- Each performer's contract: set length, sound check, arrival.
8. Walk it with the people who will run it
Read it top to bottom with the stage manager, the technical lead and the venue contact. Ask where two things need the same person or the same door at the same time. This is where missing rows turn up.
9. Send one dated version, and replace it when it changes
Put the version and date at the top. Send each vendor the part they need, not the whole sheet. There is a list by vendor type in what to send each vendor. When something changes, everyone who got the old one gets the new one.
A short worked example
An evening gala in one ballroom. Doors and the hard out are fixed. Every other start time is worked out from the lengths.
| Start | Length | Item | Owner | Notes |
|---|---|---|---|---|
| 5:30 PM | 30 min | Doors and reception | Producer | Fixed. Printed on the invitation. |
| 6:00 PM | 10 min | Welcome | Stage manager | Host on lectern microphone. |
| 6:10 PM | 50 min | Dinner service | Banquet captain | Matches the venue's order. 5 spare minutes at the end. |
| 6:45 PM | 10 min | Speaker to green room | Stage manager | 15 minutes before the keynote. Moves with it. |
| 7:00 PM | 25 min | Keynote | Stage manager | Headset microphone. Slides on centre screen. |
| 7:25 PM | 30 min | Awards | Stage manager | Cut first: the second video. |
| 7:55 PM | 55 min | Band | Technical lead | Contracted set length. |
| 8:50 PM | 10 min | Goodnight and exit | Producer | Venue hard out 9:00 PM. |
Mistakes that cost the most
- Typing every start time by hand, so one change means retyping the night.
- Back-of-house rows with fixed times that stay put when the item they serve moves.
- Rows owned by a department, not a person.
- No buffer anywhere, and no decision about what to cut.
- Service times that differ from the venue's order.
- Three versions in circulation and no date on any of them.
Common questions
What do I need before I start a run of show?
The fixed points: when doors open, when you must be out of the venue, the meal service times, and any contracted set lengths. Then the list of what happens, in order.
Should I type start times or lengths?
Lengths. Type how long each item runs and work out each start from the item before it. Only times that cannot move, such as doors, get typed in. Then one change updates everything after it.
How much buffer should a run of show have?
There is no fixed rule. Most producers put a few spare minutes after a meal, before the main speaker and at each changeover, and decide in advance what they would cut if the night runs long.
Who builds the run of show?
Usually the producer, or the person who will call the show. On small events it is often the planner. Whoever builds it should walk it with the stage manager, the technical lead and the venue before it goes out.
When should the run of show be finished?
Start a working draft as soon as the program is known, so vendors can plan around it. Teams differ on when they lock it. What matters is that one dated version goes to everyone, and that any later change replaces it for everyone.